Home
Up

 

Welded Tube (5)

From Steel to Tube
An overview of welded tube manufacture (continued)
 

CONTROL OF PIPE QUALITY AT THE WELDING MILL
   The quality of EW weld is assessed by standard destructive tests such as cone expansion and flattening and by inspecting the microstructure of the weld area. This testing augments the non-destructive testing and provides a regular feedback to the mill on weld quality.
  The objective is to ensure that the weld area is as strong, if not stronger than the body of the pipe. The microstructure is inspected to ensure that the heat affected zone is symmetrical and satisfactory with regard to width and structure, that there is adequate diversion and that all the previously liquid metal and oxides have been removed from the weld region. Having established that the welding conditions are correct and that the weld is satisfactory it is then essential to ensure that the conditions under which the sample was taken do not change.
   There are many aspects of the pipe making process, which affect weld quality. These include setting of the forming mill, strip presentation to the forming mill, consistent width dimensions of the ingoing strip and control of the welding temperature.
   The two main variables, which can affect the weld temperature are the strip speed and thickness of the strip edge. The welding power is proportional to strip speed and strip thickness and the welding power requirement is measured using a constant called the energy factor. The energy factor is the welding power in watts per mm thickness per metre, per minute speed (watt min/mm²).
   Strip speed variation is dealt with by measuring the strip speed with a wheel driving a measuring instrument, which runs on the strip and is used to control the welder power output. Any variation in strip speed is therefore directly compensated for.
   Strip edge thickness is governed by the thickness of the slit strip plus thickening occurring in the fin pass rolls, which is impractical to measure.
   The most effective way of compensating for edge thickness and other variations is by keeping the temperature of the weld region constant. This is measured immediately after the formation of the weld with a two colour pyrometer which is unaffected by steam and water. The temperature measurement is used in a computerised control loop to adjust the speed power system to maintain a constant weld temperature.

STRETCH REDUCTION AND HEAT TREATMENT
   For pipe diameters of 139.7mm or less and wall thicknesses of 7.9mm or less, a 168.3mm diameter pipe is produced at the EW Mill and stretch reduced to the required finished size.The 168.3mm as welded pipe is heated in a 122m long gas fired barrel furnace followed by a 10m in line 10 megawatt induction furnace to about 1000°C, and stretch reduced through a series of water cooled rolls to the required size.  After cooling, the pipes are cut to the required length and either sent to the visual inspection tables or for quenching and tempering.  All pipes of diameter greater than 139.7mm or thickness greater than 7.9mm are formed to dimensions close to the finished size on the welding mill and heat treated using one of the following three methods. The weld line only may be heated to the normalising temperature using in line induction heaters, the complete pipes may be normalised in a separate furnace or for higher strengths, the pipes may be quenched and tempered.  The pipes passing on to the quench unit are heated rapidly in a gas fired barrel furnace to 850-950°C and are water quenched on the outside surface by passing through 20 in-line spray rings as soon as they leave the furnace.  To aid even heating and cooling, pipes are rotated on passing through the unit and a pyrometer is used to monitor the temperature at the furnace exit prior to quenching to ensure temperatures within the required range are obtained. Hardness’s are measured on the transverse faces of rings cut from each quenched batch to ensure sufficient through wall hardening has occurred.  Normalising and tempering is done in gas fired walking beam or electric roller hearth furnaces where the pipes are maintained at an accurately controlled temperature for about 10 minutes and are then removed from the furnace to cool in air.

INSPECTION
   The bore and the outside surfaces of each pipe are visually inspected and the reasons for rejection recorded and analysed. The diameter, thickness and degree of ovality of each end of each pipe are checked. The pipes are bevelled and hydrostatically tested using the conditions laid down in the API specifications. If the pipes are to be subsequently threaded this test may be done at a later stage. The pipes are then sent for rotary probe ultrasonic testing, 

Previous Page

Products  Chinese   News  Company Ultrasonics Links

 

Contact Information:          Telephone (+44) 1536 406664   Fax   (+44) 1536 266635    E-mail General Enquiries
Postal  Address
: Unicorn Automation (NDT) Ltd. Cavendish Courtyard Weldon North Industrial Estate, Corby, Northants NN17 5DZ,UK
Registered in England No. 2824838   Copyright © 2003-2007 Unicorn Automation (NDT) Ltd.